How are telecom towers delivered worldwide?
A telecom tower reaches its site in six steps: design, fabrication, trial assembly, packing and freight, import clearance and inland transport. The delivery term decides who is responsible at each step, and most problems start at a handover.
A 60-metre lattice tower leaves the factory as several hundred galvanised steel members and thousands of bolts. If one bundle is missing when the crew arrives on site, the build stops. Worldwide delivery is therefore less about shipping and more about control at every handover.
The six steps
- Design. The tower is calculated for the wind speed, antenna loading and design code of the destination. A tower for a typhoon zone in the Philippines is not the same tower as one for inland Tanzania.
- Fabrication and galvanising. Steel is cut, drilled and hot-dip galvanised at the factory. GSM quality inspectors follow production.
- Trial assembly. Every new tower design is assembled at the factory before packing, so that fit problems are found there and not on a hilltop six weeks later.
- Packing and sea freight. Members are bundled and marked per tower and per section, then shipped in containers. At GSM, our own team is present at every shipment and checks it against the packing list.
- Import clearance. The importer of record, which is the supplier under DDP and normally the buyer under every other term, handles documents, duties and local taxes.
- Inland transport. The towers move by truck from port to a warehouse or directly to site.
What the delivery term changes
| Term | Supplier’s responsibility ends | Who clears import | Suits |
|---|---|---|---|
| EXW | At the factory gate | Buyer | Buyers with their own freight forwarder |
| FOB | When loaded on the vessel | Buyer | Buyers who control sea freight |
| CIF / CIP | At the destination port, freight and insurance paid | Buyer | Buyers who want one freight price and handle import themselves |
| DAP | At the agreed place in the destination country, before duties | Buyer | Buyers with an import licence who want delivery to warehouse or site |
| DDP | At the agreed place, duties paid | Supplier | Projects where the buyer cannot or will not import |
No term is best everywhere. The right one depends on who holds the import licence, who can recover local VAT and who is best placed to manage the port.
What GSM does
So far in 2026 GSM has delivered to 15 countries. We design in Norway, inspect fabrication and trial assembly at the factory and check every shipment before it leaves. Most of our deliveries are EXW, FOB, CIF/CIP or DAP. Where a project requires it, we deliver duty-paid. In the Philippines we import through our own licensed company, and in Ireland and Germany GSM Towers is the importer.
In short: compare suppliers on the same delivery term, and ask who is responsible when a part is missing on site.